Dubai Land Department records

Developer

TRANQUIL INFRA DEVELOPERS L.L.C

DLD developer number 1812Registered with DLD on 25 Dec 2023

On the DLD projects register

Projects
2
Live
2
Completed
0
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
1

A planned completion date moved once since we started checking in Oct 2026, on 1 of 2 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Blossom 40
    Registered status: Not started
    0% complete

    Wadi Al Safa 3 · 66 units, 1 building

    Started
    01 Feb 2026
    Current planned completion
    31 Mar 2028

    12 unit and villa sales in the year to Sep 2026

  2. Blossom 76 by Tranquil
    Registered status: Active
    40% complete

    Al Barsha South Fourth · 113 units, 1 building

    Started
    15 Aug 2024
    Current planned completion
    26 Mar 2027

    Planned date moved once since we started checking in Oct 2026

    44 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.