Developer
WADAN REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 2166Registered with DLD on 10 Dec 2024
On the DLD projects register
- Projects
- 5
- Live
- 5
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 2
No planned completion date has moved since we started checking in Oct 2026, across 5 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- WESTONRegistered status: Not started0% complete
Wadi Al Safa 5 · 373 units, 1 building
- Started
- 15 Aug 2026
- Current planned completion
- 31 Dec 2028
8 unit and villa sales in the year to Sep 2026
- Tresora by WadanRegistered status: Not started0% complete
Al Barsha South Fourth · 160 units, 1 building
- Started
- 30 Mar 2026
- Current planned completion
- 30 Mar 2028
83 unit and villa sales in the year to Sep 2026
- Cybele By WadanRegistered status: Active2% complete
Wadi Al Safa 5 · 232 units, 1 building
- Started
- 30 Dec 2025
- Current planned completion
- 30 Dec 2027
223 unit and villa sales in the year to Sep 2026
- Seraph by WadanRegistered status: Active20.9% complete
Wadi Al Safa 5 · 190 units, 1 building
- Started
- 15 Dec 2025
- Current planned completion
- 15 Dec 2027
188 unit and villa sales in the year to Sep 2026
- Nuvana by WadanRegistered status: Active24.9% complete
Palm Deira · 57 units, 1 building
- Started
- 01 Sep 2025
- Current planned completion
- 01 Sep 2027
57 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.