Developer
ZENITH VENTURES REAL ESTATE DEVELOPMENT L.L.C
DLD developer number 1675Registered with DLD on 01 Aug 2023
On the DLD projects register
- Projects
- 3
- Live
- 3
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 1
No planned completion date has moved since we started checking in Oct 2026, across 3 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4545Registered status: Pending0% complete
Madinat Al Mataar · 121 units, 1 building
- Started
- 01 Aug 2026
- Current planned completion
- 29 Jul 2029
- DLD project 4087Registered status: Pending20.1% complete
Madinat Al Mataar · 64 units, 1 building
- Started
- 25 Sep 2025
- Current planned completion
- 14 May 2028
- Zenith Tower J1Registered status: Active72.2% complete
Al Barsha South Fourth · 76 units, 1 building
- Started
- 27 Sep 2023
- Current planned completion
- 25 Dec 2026
5 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.