AZIZI VISTA and LAYA HEIGHTS compared
Two to four areas, or two to four projects, side by side: the median sale price, rental yield and price change the nightly market build published for each, with the sales and contracts every figure rests on. Nothing is ranked or scored.
Off-plan sales mix developer launch prices and resales of units and villas not yet built, so they are never in the same median as ready sales.
Rental yield, from DLD sale transactions and Ejari rent contracts
AZIZI VISTA
- Gross rental yield
- Too few ready sales (18 kept, 30 needed)
- 73 new tenancies and 18 ready sales kept
- Jul 2025 – Jun 2026
LAYA HEIGHTS
- Gross rental yield
- Too few ready sales (18 kept, 30 needed)
- 59 new tenancies and 18 ready sales kept
- Jul 2025 – Jun 2026
Median annual rent of new tenancies over the median price of ready sales, before service charges.
| Figure | AZIZI VISTAIn Al Hebiah Second55 unit and villa sales in the year to 30 Sep 2026 | LAYA HEIGHTSIn Al Hebiah Second53 unit and villa sales in the year to 30 Sep 2026 |
|---|---|---|
| Rental yield, from DLD sale transactions and Ejari rent contracts | ||
| Gross rental yield |
|
|
Median annual rent of new tenancies over the median price of ready sales, before service charges. | ||
DLD register records
AZIZI VISTA
- Registered status
- Finished
- Percent complete
- 100%
- Planned completion
- 30 Apr 2025
- Not since we started checking in Oct 2026
- Completed or cancelled
- Completed 30 Sep 2025
- Developer
- AZIZI DEVELOPMENTS L.L.C
- 59 live, 91 completed, 0 cancelled, 150 projects in all
LAYA HEIGHTS
- Registered status
- Finished
- Percent complete
- 100%
- Planned completion
- 30 Nov 2023
- Not since we started checking in Oct 2026
- Completed or cancelled
- Completed 30 Nov 2023
- Developer
- LAYA DEVELOPERS L.L.C
- 2 live, 3 completed, 0 cancelled, 5 projects in all
The register's own dates, as it holds them today. This page gives no on-time verdict and no developer rating.
Source: DLD projects and developers registers, read 19 Nov 2026.
| Figure | AZIZI VISTAIn Al Hebiah Second55 unit and villa sales in the year to 30 Sep 2026 | LAYA HEIGHTSIn Al Hebiah Second53 unit and villa sales in the year to 30 Sep 2026 |
|---|---|---|
| DLD register records | ||
| Registered status | Finished | Finished |
| Percent complete | 100% | 100% |
| Planned completion | 30 Apr 2025
| 30 Nov 2023
|
| Completed or cancelled | Completed 30 Sep 2025 | Completed 30 Nov 2023 |
| Developer | AZIZI DEVELOPMENTS L.L.C
| LAYA DEVELOPERS L.L.C
|
The register's own dates, as it holds them today. This page gives no on-time verdict and no developer rating. Source: DLD projects and developers registers, read 19 Nov 2026. | ||
Updated with each nightly build. Sales through 16 Nov 2026. Published 19 Nov 2026.Sources: DLD sale transactions and Ejari rent contracts.How we check the figures
How to read this comparison
Each figure is a median of what sold or was rented over the trailing year of four quarters, after the plausibility rule. A median describes the sales in its window, not what a given unit or villa is worth, and two places can differ because a different mix of units or villas sold in each.
A figure resting on too few sales is withheld rather than shown, and the cell says how many were kept. The places keep the order the API gives them, by page address: nothing on this page is sorted by a figure.