Skip to content
Homes
Dubai Land Department records

Developer

EMPIRE REAL ESTATE DEVELOPMENTS L.L.C

DLD developer number 1794Registered with DLD on 07 Dec 2023

On the DLD projects register

Projects
2
Live
2
Completed
0
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
0

No planned completion date has moved since we started checking in Oct 2026, across 2 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. Empire Livings
    Registered status: Active
    13.3% complete

    Al Barshaa South Second · 210 units, 1 building

    Started
    30 Nov 2024
    Current planned completion
    30 Nov 2027

    70 unit and villa sales in the year to Sep 2026

  2. Empire Estates
    Registered status: Active
    60% complete

    Al Barshaa South Third · 344 units, 1 building

    Started
    01 Jan 2024
    Current planned completion
    31 Dec 2026

    100 unit and villa sales in the year to Sep 2026

Source: DLD projects register, read 11 Nov 2026.