Developer
Expo City Mangrove Residences Development FZCO
DLD developer number 1574Registered with DLD on 07 Mar 2023
On the DLD projects register
- Projects
- 1
- Live
- 1
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 0
No planned completion date has moved since we started checking in Oct 2026, across 1 project.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- Expo City Mangrove ResidencesRegistered status: Active91.2% complete
Madinat Al Mataar · 470 units, 3 buildings
- Started
- 01 Jun 2023
- Current planned completion
- 31 Jan 2026
59 unit and villa sales in the year to Sep 2026
Source: DLD projects register, read 11 Nov 2026.