- Projects
- 18
- Live
- 10
- Completed
- 8
- Cancelled
- 0
- Planned completion in the next 12 months
- 1
- Started in 2026
- 3
No planned completion date has moved since we started checking in Oct 2026, across 18 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4574Registered status: Pending0% complete
Al Barshaa South Second
- Started
- 03 Dec 2026
- Current planned completion
- 03 Dec 2029
- 113 RESIDENCESRegistered status: Not started0% complete
Al Safouh First · 113 units, 1 building
- Started
- 25 Aug 2026
- Current planned completion
- 28 Feb 2029
42 unit and villa sales in the year to Sep 2026
- OXFORD COVERegistered status: Not started0% complete
Al Barsha South Fourth · 253 units, 1 building
- Started
- 10 May 2026
- Current planned completion
- 30 Mar 2029
154 unit and villa sales in the year to Sep 2026
- SIERRA BY IMANRegistered status: Active3.7% complete
Al Hebiah First · 598 units, 1 building
- Started
- 01 Nov 2025
- Current planned completion
- 30 Jun 2029
522 unit and villa sales in the year to Sep 2026
- 15 CASCADERegistered status: Active5.5% complete
Al Hebiah First · 442 units, 1 building
- Started
- 30 Mar 2025
- Current planned completion
- 30 Sep 2028
178 unit and villa sales in the year to Sep 2026
- ONE PARK SQUARE BY IMANRegistered status: Active20.1% complete
Al Barsha South Fourth · 269 units, 1 building
- Started
- 01 Jan 2025
- Current planned completion
- 30 Jun 2028
16 unit and villa sales in the year to Sep 2026
- ONE SKY PARK BY IMANRegistered status: Active21.7% complete
Al Barsha South Fourth · 584 units, 2 buildings
- Started
- 01 Oct 2024
- Current planned completion
- 30 Mar 2028
61 unit and villa sales in the year to Sep 2026
- 10 OXFORD by IMANRegistered status: Active91.3% complete
Al Barsha South Fourth · 430 units, 2 buildings
- Started
- 29 Apr 2024
- Current planned completion
- Not published
33 unit and villa sales in the year to Sep 2026
- ONE PARK CENTRAL BY IMANRegistered status: Active20.1% complete
Al Barsha South Fourth · 526 units, 1 building
- Started
- 25 Apr 2024
- Current planned completion
- 30 Jun 2027
19 unit and villa sales in the year to Sep 2026
- GARDENS 2Registered status: Active68.5% complete
Al Barshaa South Third · 223 units, 1 building
- Started
- 20 Apr 2024
- Current planned completion
- 30 Dec 2025
31 unit and villa sales in the year to Sep 2026
- Oxford GardensRegistered status: Finished
Al Barshaa South Third · 240 units, 1 building
- Started
- 11 Jul 2023
- Current planned completion
- 30 Mar 2025
- Completed
- 24 Sep 2025
68 unit and villa sales in the year to Sep 2026
- OXFORD TERRACES 2Registered status: Finished
Al Barsha South Fourth · 101 units, 1 building
- Started
- 15 Feb 2023
- Current planned completion
- 15 Nov 2024
- Completed
- 15 Nov 2024
9 unit and villa sales in the year to Sep 2026
6 more projects
- THE GROVE BY IMANRegistered status: Finished
Hadaeq Sheikh Mohammed Bin Rashid · 125 units, 1 building
- Started
- 01 Nov 2022
- Current planned completion
- 30 Aug 2024
- Completed
- 30 Aug 2024
12 unit and villa sales in the year to Sep 2026
- Oxford TerracesRegistered status: Finished
Al Barsha South Fourth · 117 units, 1 building
- Started
- 15 May 2022
- Current planned completion
- 15 Jan 2024
- Completed
- 15 Jan 2024
5 unit and villa sales in the year to Sep 2026
- Oxford 212Registered status: Finished
Al Barsha South Fourth · 212 units, 1 building
- Started
- 08 Aug 2021
- Current planned completion
- 28 Feb 2023
- Completed
- 28 Feb 2023
25 unit and villa sales in the year to Sep 2026
- OXFORD BOULEVARDRegistered status: Finished
Al Barsha South Fourth · 131 units, 1 building
- Started
- 07 Oct 2019
- Current planned completion
- 06 Oct 2021
- Completed
- 06 Oct 2021
6 unit and villa sales in the year to Sep 2026
- OXFORD RESIDENCE 2Registered status: Finished
Al Barsha South Fourth · 147 units, 1 building
- Started
- 04 Jun 2018
- Current planned completion
- 27 Apr 2020
- Completed
- 10 Mar 2020
13 unit and villa sales in the year to Sep 2026
- Oxford ResidenceRegistered status: Finished
Al Barsha South Fourth · 103 units, 1 building
- Started
- 10 Sep 2016
- Current planned completion
- 28 Feb 2018
- Completed
- 28 Feb 2018
7 unit and villa sales in the year to Sep 2026