Skip to content
Homes
Dubai Land Department records

Developer

IMAN DEVELOPERS L.L.C

DLD developer number 1178Registered with DLD on 08 Mar 2017

On the DLD projects register

Projects
18
Live
10
Completed
8
Cancelled
0
Planned completion in the next 12 months
1
Started in 2026
3

No planned completion date has moved since we started checking in Oct 2026, across 18 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 4574
    Registered status: Pending
    0% complete

    Al Barshaa South Second

    Started
    03 Dec 2026
    Current planned completion
    03 Dec 2029
  2. 113 RESIDENCES
    Registered status: Not started
    0% complete

    Al Safouh First · 113 units, 1 building

    Started
    25 Aug 2026
    Current planned completion
    28 Feb 2029

    42 unit and villa sales in the year to Sep 2026

  3. OXFORD COVE
    Registered status: Not started
    0% complete

    Al Barsha South Fourth · 253 units, 1 building

    Started
    10 May 2026
    Current planned completion
    30 Mar 2029

    154 unit and villa sales in the year to Sep 2026

  4. SIERRA BY IMAN
    Registered status: Active
    3.7% complete

    Al Hebiah First · 598 units, 1 building

    Started
    01 Nov 2025
    Current planned completion
    30 Jun 2029

    522 unit and villa sales in the year to Sep 2026

  5. 15 CASCADE
    Registered status: Active
    5.5% complete

    Al Hebiah First · 442 units, 1 building

    Started
    30 Mar 2025
    Current planned completion
    30 Sep 2028

    178 unit and villa sales in the year to Sep 2026

  6. ONE PARK SQUARE BY IMAN
    Registered status: Active
    20.1% complete

    Al Barsha South Fourth · 269 units, 1 building

    Started
    01 Jan 2025
    Current planned completion
    30 Jun 2028

    16 unit and villa sales in the year to Sep 2026

  7. ONE SKY PARK BY IMAN
    Registered status: Active
    21.7% complete

    Al Barsha South Fourth · 584 units, 2 buildings

    Started
    01 Oct 2024
    Current planned completion
    30 Mar 2028

    61 unit and villa sales in the year to Sep 2026

  8. 10 OXFORD by IMAN
    Registered status: Active
    91.3% complete

    Al Barsha South Fourth · 430 units, 2 buildings

    Started
    29 Apr 2024
    Current planned completion
    Not published

    33 unit and villa sales in the year to Sep 2026

  9. ONE PARK CENTRAL BY IMAN
    Registered status: Active
    20.1% complete

    Al Barsha South Fourth · 526 units, 1 building

    Started
    25 Apr 2024
    Current planned completion
    30 Jun 2027

    19 unit and villa sales in the year to Sep 2026

  10. GARDENS 2
    Registered status: Active
    68.5% complete

    Al Barshaa South Third · 223 units, 1 building

    Started
    20 Apr 2024
    Current planned completion
    30 Dec 2025

    31 unit and villa sales in the year to Sep 2026

  11. Oxford Gardens
    Registered status: Finished

    Al Barshaa South Third · 240 units, 1 building

    Started
    11 Jul 2023
    Current planned completion
    30 Mar 2025
    Completed
    24 Sep 2025

    68 unit and villa sales in the year to Sep 2026

  12. OXFORD TERRACES 2
    Registered status: Finished

    Al Barsha South Fourth · 101 units, 1 building

    Started
    15 Feb 2023
    Current planned completion
    15 Nov 2024
    Completed
    15 Nov 2024

    9 unit and villa sales in the year to Sep 2026

6 more projects
  1. THE GROVE BY IMAN
    Registered status: Finished

    Hadaeq Sheikh Mohammed Bin Rashid · 125 units, 1 building

    Started
    01 Nov 2022
    Current planned completion
    30 Aug 2024
    Completed
    30 Aug 2024

    12 unit and villa sales in the year to Sep 2026

  2. Oxford Terraces
    Registered status: Finished

    Al Barsha South Fourth · 117 units, 1 building

    Started
    15 May 2022
    Current planned completion
    15 Jan 2024
    Completed
    15 Jan 2024

    5 unit and villa sales in the year to Sep 2026

  3. Oxford 212
    Registered status: Finished

    Al Barsha South Fourth · 212 units, 1 building

    Started
    08 Aug 2021
    Current planned completion
    28 Feb 2023
    Completed
    28 Feb 2023

    25 unit and villa sales in the year to Sep 2026

  4. OXFORD BOULEVARD
    Registered status: Finished

    Al Barsha South Fourth · 131 units, 1 building

    Started
    07 Oct 2019
    Current planned completion
    06 Oct 2021
    Completed
    06 Oct 2021

    6 unit and villa sales in the year to Sep 2026

  5. OXFORD RESIDENCE 2
    Registered status: Finished

    Al Barsha South Fourth · 147 units, 1 building

    Started
    04 Jun 2018
    Current planned completion
    27 Apr 2020
    Completed
    10 Mar 2020

    13 unit and villa sales in the year to Sep 2026

  6. Oxford Residence
    Registered status: Finished

    Al Barsha South Fourth · 103 units, 1 building

    Started
    10 Sep 2016
    Current planned completion
    28 Feb 2018
    Completed
    28 Feb 2018

    7 unit and villa sales in the year to Sep 2026

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.