Developer
NAS ESTATES L.L.C
DLD developer number 1762Registered with DLD on 01 Nov 2023
On the DLD projects register
- Projects
- 8
- Live
- 8
- Completed
- 0
- Cancelled
- 0
- Planned completion in the next 12 months
- 0
- Started in 2026
- 2
No planned completion date has moved since we started checking in Oct 2026, across 8 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4352Registered status: Not started0% complete
Nad Al Shiba First · 96 land plots
- Started
- 01 Mar 2026
- Current planned completion
- 01 Aug 2029
- Nad Al Sheba Gardens Phase 11Registered status: Not started0.1% complete
Nad Al Shiba First · 210 villas, 120 land plots
- Started
- 01 Feb 2026
- Current planned completion
- 01 Jul 2029
110 unit and villa sales in the year to Sep 2026
- Nad Al Sheba Gardens Phase 10Registered status: Not started0.4% complete
Nad Al Shiba First · 201 villas, 115 land plots
- Started
- 01 Sep 2025
- Current planned completion
- 01 Oct 2028
80 unit and villa sales in the year to Sep 2026
- DLD project 3860Registered status: Active0.7% complete
Nad Al Shiba First · 201 villas, 152 land plots
- Started
- 01 Sep 2025
- Current planned completion
- 01 Oct 2028
- Nad Al Sheba Gardens Phase 7Registered status: Active4% complete
Nad Al Shiba First · 272 villas, 144 land plots
- Started
- 28 Jan 2025
- Current planned completion
- 15 Feb 2028
8 unit and villa sales in the year to Sep 2026
- Nad Al Sheba Gardens Phase 5Registered status: Active37.5% complete
Nad Al Shiba First · 159 villas, 81 land plots
- Started
- 01 Oct 2024
- Current planned completion
- Not published
14 unit and villa sales in the year to Sep 2026
- Nad Al Sheba Gardens Phase 6Registered status: Active13.9% complete
Nad Al Shiba First · 100 villas, 61 land plots
- Started
- 01 Oct 2024
- Current planned completion
- Not published
5 unit and villa sales in the year to Sep 2026
- Nad AL Sheba Gardens Phase 4Registered status: Active76.3% complete
Nad Al Shiba First · 188 villas, 111 land plots
- Started
- 01 May 2024
- Current planned completion
- Not published
17 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.