Dubai Land Department records

Developer

REEF LUXURY DEVELOPMENT L.L.C

DLD developer number 1944Registered with DLD on 21 May 2024

On the DLD projects register

Projects
7
Live
7
Completed
0
Cancelled
0
Planned completion in the next 12 months
3
Started in 2026
1

No planned completion date has moved since we started checking in Oct 2026, across 7 projects.

These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.

Source: DLD developers and projects registers, read 11 Nov 2026.

Projects

Newest start first. Each bar runs from the start date to the register's current planned completion date.

  1. DLD project 4285
    Registered status: Not started
    0% complete

    Wadi Al Safa 5 · 347 units, 1 building

    Started
    01 Feb 2026
    Current planned completion
    30 Nov 2028
  2. Reef 996
    Registered status: Not started
    0.1% complete

    Me'Aisem First · 505 units, 1 building

    Started
    01 Oct 2025
    Current planned completion
    30 Sep 2028

    231 unit and villa sales in the year to Sep 2026

  3. 997 Residences by Reef Luxury Development
    Registered status: Active
    4.9% complete

    Palm Deira · 63 units, 1 building

    Started
    15 Jul 2025
    Current planned completion
    30 Mar 2028

    20 unit and villa sales in the year to Sep 2026

  4. Reef 998
    Registered status: Active
    2.1% complete

    Wadi Al Safa 5 · 339 units, 1 building

    Started
    01 Jun 2025
    Current planned completion
    30 Jun 2028

    198 unit and villa sales in the year to Sep 2026

  5. 999 Residences by Reef Luxury Development
    Registered status: Active
    13.2% complete

    Jabal Ali First · 148 units, 2 buildings

    Started
    01 Apr 2025
    Current planned completion
    30 Jun 2027

    68 unit and villa sales in the year to Sep 2026

  6. REEF 1000
    Registered status: Active
    67.2% complete

    Wadi Al Safa 5 · 126 units, 1 building

    Started
    01 Nov 2024
    Current planned completion
    30 Dec 2026

    34 unit and villa sales in the year to Sep 2026

  7. DLD project 4610
    Registered status: Pending
    70% complete

    Jumeirah First

    Started
    24 Aug 2024
    Current planned completion
    23 Feb 2027

A project without a page on this site is named by its DLD project number.

Source: DLD projects register, read 11 Nov 2026.