Developer
NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C
DLD developer number 1162Registered with DLD on 08 Nov 2016
On the DLD projects register
- Projects
- 40
- Live
- 24
- Completed
- 16
- Cancelled
- 0
- Planned completion in the next 12 months
- 6
- Started in 2026
- 6
No planned completion date has moved since we started checking in Oct 2026, across 40 projects.
These are the register's current dates. A planned date that moved before we started checking isn't recorded, so this page doesn't say whether a project finished on time.
Source: DLD developers and projects registers, read 11 Nov 2026.
Projects
Newest start first. Each bar runs from the start date to the register's current planned completion date.
- DLD project 4436Registered status: Pending0% complete
Al Yelayiss 2
- Started
- 17 Aug 2026
- Current planned completion
- 31 May 2029
- DLD project 4337Registered status: Not started0% complete
Al Yelayiss 2 · 281 units, 1 building
- Started
- 20 Jul 2026
- Current planned completion
- 30 Apr 2029
- Evelyn on the ParkRegistered status: Not started0% complete
Al Yelayiss 2 · 259 units, 1 building
- Started
- 15 Jun 2026
- Current planned completion
- 28 Feb 2029
168 unit and villa sales in the year to Sep 2026
- ROSEWELLRegistered status: Not started0% complete
Al Yelayiss 2 · 217 units, 1 building
- Started
- 15 Apr 2026
- Current planned completion
- 31 Dec 2028
177 unit and villa sales in the year to Sep 2026
- FioriRegistered status: Not started0% complete
Al Yelayiss 2 · 146 units, 1 building
- Started
- 16 Mar 2026
- Current planned completion
- 30 Jun 2028
112 unit and villa sales in the year to Sep 2026
- OlbiaRegistered status: Not started0% complete
Al Yelayiss 2 · 156 units, 1 building
- Started
- 30 Jan 2026
- Current planned completion
- 31 May 2028
94 unit and villa sales in the year to Sep 2026
- CamdenRegistered status: Active7.2% complete
Al Yelayiss 2 · 168 units, 1 building
- Started
- 20 Dec 2025
- Current planned completion
- 31 Mar 2028
103 unit and villa sales in the year to Sep 2026
- AltonRegistered status: Active5.2% complete
Al Yelayiss 2 · 149 units, 1 building
- Started
- 01 Nov 2025
- Current planned completion
- 31 May 2028
48 unit and villa sales in the year to Sep 2026
- AugustaRegistered status: Active5.3% complete
Al Yelayiss 2 · 154 units, 1 building
- Started
- 10 Oct 2025
- Current planned completion
- 14 Jan 2028
18 unit and villa sales in the year to Sep 2026
- OdessaRegistered status: Active8% complete
Al Yelayiss 2 · 178 units, 1 building
- Started
- 25 Aug 2025
- Current planned completion
- 30 Dec 2027
27 unit and villa sales in the year to Sep 2026
- EllisonRegistered status: Active40.2% complete
Al Yelayiss 2 · 148 units, 1 building
- Started
- 14 Jul 2025
- Current planned completion
- 30 Nov 2027
12 unit and villa sales in the year to Sep 2026
- ADDRESS GRAND DOWNTOWNRegistered status: Active10.8% complete
Burj Khalifa · 80 units, 1 building
- Started
- 10 Jun 2025
- Current planned completion
- 10 Jun 2028
1 unit or villa sale in the year to Sep 2026
28 more projects
- The BaltimoreRegistered status: Active26.3% complete
Al Yelayiss 2 · 167 units, 1 building
- Started
- 18 May 2025
- Current planned completion
- 30 Sep 2027
22 unit and villa sales in the year to Sep 2026
- LexingtonRegistered status: Active4.5% complete
Al Yelayiss 2 · 142 units, 1 building
- Started
- 05 May 2025
- Current planned completion
- 30 Sep 2027
9 unit and villa sales in the year to Sep 2026
- Berkshire ParkRegistered status: Active17.6% complete
Al Yelayiss 2 · 149 units, 1 building
- Started
- 04 Mar 2025
- Current planned completion
- 30 Jun 2027
21 unit and villa sales in the year to Sep 2026
- HillcrestRegistered status: Active38.4% complete
Al Yelayiss 2 · 171 units, 1 building
- Started
- 03 Mar 2025
- Current planned completion
- 30 Jun 2027
13 unit and villa sales in the year to Sep 2026
- SavannahRegistered status: Active43.5% complete
Al Yelayiss 2 · 154 units, 1 building
- Started
- 19 Dec 2024
- Current planned completion
- 30 Apr 2027
11 unit and villa sales in the year to Sep 2026
- Haya on the ParkRegistered status: Active35.3% complete
Al Yelayiss 2 · 196 units, 1 building
- Started
- 04 Nov 2024
- Current planned completion
- 26 Feb 2027
16 unit and villa sales in the year to Sep 2026
- Lana on the ParkRegistered status: Active35.9% complete
Al Yelayiss 2 · 196 units, 1 building
- Started
- 25 Oct 2024
- Current planned completion
- Not published
20 unit and villa sales in the year to Sep 2026
- ElayaRegistered status: Finished
Al Yelayiss 2 · 153 units, 1 building
- Started
- 27 Sep 2024
- Current planned completion
- Not published
- Completed
- 26 Oct 2026
12 unit and villa sales in the year to Sep 2026
- ORARegistered status: Active47.4% complete
Al Yelayiss 2 · 157 units, 1 building
- Started
- 25 Sep 2024
- Current planned completion
- Not published
13 unit and villa sales in the year to Sep 2026
- HOLLAND GARDENSRegistered status: Finished
Al Yelayiss 2 · 228 units, 1 building
- Started
- 15 Sep 2024
- Current planned completion
- 30 Sep 2025
- Completed
- 17 Nov 2025
85 unit and villa sales in the year to Sep 2026
- FIARegistered status: Active84.6% complete
Al Yelayiss 2 · 192 units, 1 building
- Started
- 13 Sep 2024
- Current planned completion
- Not published
8 unit and villa sales in the year to Sep 2026
- KayaRegistered status: Finished
Al Yelayiss 2 · 164 units, 1 building
- Started
- 01 Aug 2024
- Current planned completion
- Not published
- Completed
- 24 Sep 2026
15 unit and villa sales in the year to Sep 2026
- GroveRegistered status: Active40.7% complete
Al Yelayiss 2 · 378 units, 2 buildings
- Started
- 20 May 2024
- Current planned completion
- Not published
41 unit and villa sales in the year to Sep 2026
- SymphonyRegistered status: Active73.2% complete
Al Yelayiss 2 · 398 units, 2 buildings
- Started
- 05 Feb 2024
- Current planned completion
- Not published
44 unit and villa sales in the year to Sep 2026
- THE MAYFAIRRegistered status: Finished
Al Yelayiss 2 · 242 units, 1 building
- Started
- 01 Dec 2023
- Current planned completion
- Not published
- Completed
- 12 Aug 2026
52 unit and villa sales in the year to Sep 2026
- The HamiltonRegistered status: Finished
Al Yelayiss 2 · 242 units, 1 building
- Started
- 01 Oct 2023
- Current planned completion
- 31 Oct 2025
- Completed
- 31 Dec 2025
87 unit and villa sales in the year to Sep 2026
- THE REGENTRegistered status: Finished
Al Yelayiss 2 · 238 units, 1 building
- Started
- 01 Jul 2023
- Current planned completion
- 31 Jul 2025
- Completed
- 31 Jul 2025
46 unit and villa sales in the year to Sep 2026
- MAHA TOWNHOUSESRegistered status: Finished
Al Yelayiss 2 · 500 villas, 61 land plots
- Started
- 01 Mar 2023
- Current planned completion
- 31 Aug 2025
- Completed
- 31 Aug 2025
101 unit and villa sales in the year to Sep 2026
- THE DIPLOMAT RESIDENCESRegistered status: Finished
Al Yelayiss 2 · 153 units, 1 building
- Started
- 01 Mar 2023
- Current planned completion
- 30 Nov 2024
- Completed
- 30 Nov 2024
22 unit and villa sales in the year to Sep 2026
- LIVARegistered status: Finished
Al Yelayiss 2 · 484 units, 1 building
- Started
- 28 Feb 2023
- Current planned completion
- 30 Sep 2025
- Completed
- 30 Sep 2025
68 unit and villa sales in the year to Sep 2026
- ASCOT RESIDENCESRegistered status: Finished
Al Yelayiss 2 · 153 units, 1 building
- Started
- 01 Feb 2023
- Current planned completion
- 01 Nov 2024
- Completed
- 01 Nov 2024
21 unit and villa sales in the year to Sep 2026
- SHAMS TOWNHOUSESRegistered status: Finished
Al Yelayiss 2 · 212 villas, 29 land plots
- Started
- 30 Sep 2022
- Current planned completion
- 30 Dec 2024
- Completed
- 30 Dec 2024
13 unit and villa sales in the year to Sep 2026
- REEM TOWNHOUSESRegistered status: Finished
Al Yelayiss 2 · 364 villas, 45 land plots
- Started
- 01 Jan 2022
- Current planned completion
- 30 Nov 2023
- Completed
- 30 Nov 2023
12 unit and villa sales in the year to Sep 2026
- DLD project 2105Registered status: Pending0% complete
Wadi Al Safa 5
- Started
- 08 Dec 2018
- Current planned completion
- Not published
- SAMA TOWNHOUSESRegistered status: Finished
Al Yelayiss 2 · 264 villas, 31 land plots
- Started
- 15 Oct 2018
- Current planned completion
- 15 Sep 2021
- Completed
- 30 Apr 2021
14 unit and villa sales in the year to Sep 2026
- NASEEM TOWNHOUSESRegistered status: Finished
Al Yelayiss 2 · 322 villas, 42 land plots
- Started
- 01 Jun 2018
- Current planned completion
- 21 Dec 2020
- Completed
- 01 Dec 2020
16 unit and villa sales in the year to Sep 2026
- UNARegistered status: Finished
Al Yelayiss 2 · 480 units, 1 building
- Started
- 01 Jan 2018
- Current planned completion
- 30 Mar 2021
- Completed
- 30 Mar 2021
37 unit and villa sales in the year to Sep 2026
- RAWDA APARTMENTSRegistered status: Finished
Al Yelayiss 2 · 748 units, 4 buildings
- Started
- 01 Jun 2017
- Current planned completion
- 20 Feb 2020
- Completed
- 20 Feb 2020
69 unit and villa sales in the year to Sep 2026
A project without a page on this site is named by its DLD project number.
Source: DLD projects register, read 11 Nov 2026.